Natcher Bridge Won't Open Until October
Posted: 12-Sep-2002 10:21PM CDT
The Natcher Bridge probably won't open until around Oct. 10. Grouting of the tables was recently completed, and now wind ties must be attached to the cables. These ties are intended to restrict the movement of the cables during high wind. Other remaining work includes pouring concrete to complete the roofs of the two towers, painting, and electrical work. The construction equipment including two large cranes must be removed. More information: Messenger-Inquirer: Bridge likely to open in Oct. (Sept. 12, 2002) | |